A pedestal mount on a near-white ground: a nine-tube pod in three rows of three on a slewing head, a gimballed multi-window sensor ball and a second camera above the head frame, a boxed cabinet carrying the Canadian Shield mark, and four articulated levelling legs on pad feet with lifting shackles along the base.
CDNS Institutional · Specification sheet

Pedestal Mount.
The Specification Sheet.


A slewing pedestal for the Ø90 bore at a fixed site. A two-axis head carrying tube pods and Canadian Shield's own sensor head, on a cabinet pedestal that holds the power, the control and the wired network, firing the Goose-family rounds off the Launch Platform's pneumatic chain.

At a glance

The Launch Platform's Chain.
Standing Still, on a Cabinet.


One tube module, one bore, one charge pressure and one stroke, carried on a two-axis pedestal head with the sensing, the interlocks, the structure and the network a fixed site needs.

Ø90.00 mm
bore, every tube, unchanged
30 bar
charge pressure, air only
18,191 N
peak reaction into the mount, per barrel
3.00 m
stroke, every barrel
36,382 N
equivalent static load into the mount, per barrel
±170°
azimuth; −3° to +75° elevation
AIR, NOT CHEMISTRY

Nothing in the energy path burns

The launch energy is compressed air. There is no warhead, no fuze, no primer, no propellant and no energetic material on the mount or in any round it fires. The round is a carrier, and it stays one in every option on it.

ONE BARREL, ONE ARM ACTION

A person turns the key for every shot

Eight permissives stand in series ahead of the arm relay, and a ninth at a site that requires canopy rounds. The relay drops when the fire command completes, so the key is turned again for the next shot and the mount returns to SAFE between shots. A cue proposes; it never authorizes.

NOTHING TRANSMITS

No antenna, no GNSS, every link wired or fibre

Detect, track, classify and cue are Canadian Shield's own, on a sensor head that is passive but for an eye-safe rangefinder under emission control. No copper leaves the head except its supply and its bond, and there is no external data port on the mount.

THE BRAKES CARRY THE SHOT

The drives lay; the brakes hold

A shot puts up to 3,274 N·m of yaw on a centred pod, orders above any laying torque. Both axis brakes are engaged before the breech may open, and they are sized at twice the worst torque of the configuration fitted.

01 · Specification

Figure by Figure, Across the Pod Options.
With the Basis of Each Beside It.


The design definition works every result across pod options of 6, 9, 12 and 16 tubes and rules none of them. Where a figure changes with the pod, all four are given.

The tube moduleThe launch case, per barrelLoads into the mount, per barrelDynamic response of the structurePedestal geometryMass, by pod optionInertia, brakes and the shotThe laying envelope and its limitsThe interlock chainAir, stored energy and the vesselPower and the networkThe sensor headEnvironment, structure and the siteAnti-tamper and site securitySustainment

The tube module

ParameterValueBasis
BoreØ90.00 mmdesign value, unchanged from the Launch Platform
Bore area63.617 cm²calculated from the Ø90 bore
Stroke3,000 mmdesign value
Barrel lengthAbout 3,500 mmthe 3.00 m stroke plus the breech length, which the shop drawing set assumes at 500 mm
Barrel stockDrawn-over-mandrel steel tube without a weld seam, to ASTM A519, AISI 4130 or equivalentthe shop drawing's general notes
Barrel wall and proof testAt least 6 mm, proof tested at 45 barthe shop drawing's general notes
Tube outside diameterØ102 mmcalculated: Ø90 + 2 × 6 mm of wall
Pod pitchAt least about 110 to 130 mmcalculated from the Ø102 mm tube with clamp clearance
Tube clampingClamps and cradle, at a safety factor of at least 2.0 on the 9,546 N mean base forcethe shop drawing, carried into the pod interface
Breech valveNormally closed solenoid, energize to open, one per barrel, rated 30 bar, port at least 95 cm²the Launch Platform design definition
Valve opening time<5 msthe Launch Platform design definition
RoundsGoose CS-110 and Encapsulator CS-111, both 1.600 kg, unchangeda requirement of the design definition; design value for the mass
Mixed loadsAllowed: both rounds share one envelope, one mass and one indexingthe Encapsulator systems package, carried into the mount
Barrels firedOne at a time; one solenoid energized at a timethe pneumatic schematic's solenoid note
Power or signal to the roundNone; the rounds are unpowereda requirement of the design definition

The launch case, per barrel

ParameterValueBasis
Charge pressure30 bar, shop-air classdesign value
Ambient pressure in the load case1.013 barthe round's design definition
Round mass1.600 kgdesign value
Obturator seal drag250 Nthe round's design definition, carried into the load case
Velocity at the muzzle189.2 m/sdesign value, interior ballistics
Muzzle energy28.64 kJcalculated: ½mv²
Peak acceleration of the round11,369 m/s², or 1,159 g, at t = 0.14 msthe round's design definition, at the start of the stroke
Mean acceleration5,966 m/s², or 608 gthe round's design definition
Time in the barrel31.7 mscalculated on constant acceleration: 2S ÷ v

Loads into the mount, per barrel

ParameterValueBasis
Gas load on the breech18,441 Ncalculated: (30 − 1.013) bar across the bore area
Peak net reaction into the mount18,191 Ncalculated: the gas load less the seal drag; it reproduces the source's peak base force
Mean base force over the stroke9,546 Ncalculated: ½mv² ÷ stroke
In-bore impulse357.3 N·scalculated: the round's momentum plus the charge gas's momentum in the bore
Equivalent static load, first sizing36,382 Ncalculated: 2.0 × the peak reaction, for a step-applied load
Factored load for member checks72,764 Ncalculated: the equivalent static load with a safety factor of 2.0 on top
Reaction at −3° and 0° elevation18,166 N horizontal with 952 N up; 18,191 N horizontalcalculated from the reaction along the bore
Reaction at 45° and +75°12,863 N each way; 4,708 N horizontal with 17,571 N downcalculated; overturning is worst at low elevation
Base overturning moment110.3 kN·m per barrelcalculated: the equivalent static load at the modelled 3.032 m trunnion height, at 0°
Anchor loadAbout 68.9 kN per anchorcalculated on an illustrative eight anchors on a 0.8 m bolt circle, before dead-load relief; the anchor design is the structural engineer's
Yaw torque on the azimuth axis9.1 kN·mcalculated at an illustrative 0.5 m lateral offset of the bore line, at 0°
Torque on the elevation axis2,365 N·mcalculated at one row pitch, 130 mm, off the trunnion axis
FatigueThe shot count over the mount's life is set per site; anchor preload is checked for load reversalthe design definition's fatigue note

Dynamic response of the structure

ParameterValueBasis
Modelled first bending mode22.8 to 34.6 Hz across the 6 to 16-tube pod optionscalculated by hand on a uniform-cantilever model carrying the rotating mass at the trunnion
Corresponding periods28.9 to 43.8 mscalculated
The shot against the periodThe peak arrives in 0.3 % to 0.5 % of a cyclecalculated; to the first mode the shot is a step
Dynamic load factor1.55 to 1.74 undamped; 1.50 to 1.69 at 2 % dampingcalculated by driving a single-degree-of-freedom oscillator with the published force history
Step factor carried2.0the design definition carries it until a modal analysis replaces it; it holds 15 % to 29 % over the first mode
Axial wave in the barrel steel5,048 m/s, crossing a 3.5 m barrel in 0.69 mscalculated; longer than the 0.14 ms rise, so the barrel does not respond as a lumped mass
Roof stool, for comparison33.8 to 51.7 Hz on a 0.60 m stoolcalculated; it is not a building's own first frequency, which belongs to the building's engineer of record
What the hand estimate does not coverLocal modes, the slewing bearing's flexibility and clearance, base and foundation flexibility, the barrel as a wave-bearing member, and measured dampingthe design definition names all five

Pedestal geometry

ParameterValueBasis
Balance point1.46 m forward of the breech facecalculated by taking moments about the pivot; the head balances there with no counterweight
Balance against tube countIt does not move: every tube carries the same masses at the same stationscalculated
Breech drop at +75°1.41 mcalculated from the balance point
Trunnion above the slewing ring1.66 mcalculated, with 0.25 m of clearance under the breech and manifold
Trunnion above the base plane3.03 mcalculated, from the modelled column and the base and bearing stack
Muzzle height at +75°5.00 m above the base plane; the pod top sits about 3.29 m up at 0° with 16 tubescalculated, from 2.04 m of barrel forward of the trunnion
If the pivot is moved to 0.8 m513 N·m per tube out of balance, needing 392 kg of counterweight at 6 tubes and 1,047 kg at 16calculated, for a counterweight 0.8 m aft of the trunnion
BalancerA spring balancer where the pivot is moved; a gas strut is not proposed, because it is one more pressure device at the sitethe design definition's balance study
Slewing bearingFour-point-contact ball or crossed-roller, selected against the tilting moment plus the dead-load moments of an overhung podthe design definition
ConstructionA steel weldment to CSA S16, welds to CSA W59the design basis named in the design definition and the shop drawing
Cabinet contentsDisconnect, supply and uninterruptible supply; the controller; the fibre terminations; the track and cue computerthe design definition

Mass, by pod option

ParameterValueBasis
The configuration these masses describeA single centred pod on 3,500 mm barrels, ready rounds in the tubes, a shared head plenum and a bolted plinththe mass ledger's stated configuration
Barrels298 / 448 / 597 / 796 kg at 6 / 9 / 12 / 16 tubescalculated, from the mass ledger
Breeches, valves and manifold72 / 108 / 144 / 192 kgcalculated, from the mass ledger
Pod cradle and clamps104 / 157 / 209 / 278 kgcalculated, from the mass ledger
Head frame, trunnions, balancer, elevation drive and brake134 / 201 / 269 / 358 kgcalculated, from the mass ledger
Ready rounds in the tubes10 / 14 / 19 / 26 kgcalculated at 1.600 kg per round
Rotating mass648 / 958 / 1,267 / 1,679 kgcalculated, from the mass ledger
Slewing bearing, azimuth drive and brake168 / 190 / 213 / 235 kgcalculated, from the mass ledger
Pedestal: plate, stiffeners, column and cabinet fit-out575 kg on every pod optioncalculated, from the mass ledger
Mount, less the bank and the compressor1,392 / 1,723 / 2,055 / 2,489 kgcalculated, from the mass ledger
Centre of mass above the base plane1.76 / 1.98 / 2.13 / 2.27 mcalculated, with the bank and the compressor in a separate enclosure at grade
Base, as steel225 kg bolted plinth; 244 kg embedded socket, Ø700 × 12 mm and 1.2 m deep; 180 kg on four legscalculated, from the mass ledger; concrete and ballast are not machine mass
One barrel tube49.7 kg at 3,500 mm; 42.6 kg at 3,000 mmcalculated from the steel section; four of the shorter tubes reproduce the shop drawing's 170 kg
The one check on the modelThe reference four-tube system rebuilds at 673 kg against about 640 kg published, +5.1 %calculated; it is the only check the model has, and nothing has been weighed

Inertia, brakes and the shot

ParameterValueBasis
Azimuth moment of inertia646 / 969 / 1,303 / 1,738 kg·m² at 6 / 9 / 12 / 16 tubescalculated, from the inertia ledger
Elevation moment of inertia642 / 969 / 1,292 / 1,738 kg·m²calculated, from the inertia ledger
Twin pods at an illustrative ±0.5 mAzimuth moment 2,054 kg·m² on twin 8-tube podscalculated: each pod's mass moved out to ±0.5 m
Worst bore-line offset from the azimuth axis0.120 m at 6 and 9 tubes; 0.180 m at 12 and 16calculated from the pod array on a 120 mm pitch
Shot yaw torque, single centred pod2,183 N·m at 6 and 9 tubes; 3,274 N·m at 12 and 16calculated: the peak reaction on the worst offset at 0°
Shot pitch torque, single centred pod1,091 / 2,183 / 2,183 / 3,274 N·mcalculated
Shot yaw torque, twin 8-tube pods at 0.5 m12,370 N·m, on a 0.680 m worst offsetcalculated
Design brake torque4.4 kN·m at 6 and 9 tubes; 6.5 kN·m at 12 and 16; 24.7 kN·m on twin 8-tube podsa requirement: 2.0 × the worst torque of the configuration fitted
BrakesSpring-applied on both axes; the fire command waits on both of them engageda requirement of the design definition
Head rotation if a brake let go for one shot3.8°/s at 6 tubes; 2.1°/s at 16, which is well under a tenth of a degree while the round is in the borecalculated from the in-bore angular impulse; a brake is sized on torque, not on rotation
StowA sensed stow lock pins the head at a stow attitude whenever the mount is SAFE and unattendeda requirement of the design definition

The laying envelope and its limits

ParameterValueBasis
Azimuth±170°a requirement: no wider than the reference envelope, and narrowed per site in hardware
Elevation−3° to +75°a requirement: no wider than the reference envelope, and narrowed per site in hardware
Continuous rotationNot carried; the azimuth is the reference envelopethe design definition
Limit, first layerMechanical hard stops at the fixed limitsthe design definition
Limit, second layerCam-operated limit switches on both axes, wired into the sector permissive ahead of the arm relaythe design definition
The cam setSite hardware, cut from the site's surveyed footprint map, sealed and recorded, changed only under a controlled procedurethe design definition and the safety case
Limit, third layerA laying solution outside the envelope is refused before the drives movethe published Launch Platform sheet
Limit, fourth layerThe site no-fire map, loaded into the laying software as a cross-check; it never replaces the cam switchesthe design definition
Boresight and levelThe sensor head is boresighted to the barrels against a stored offset; a tilt switch confirms the base is within tolerance before the mount will armthe design definition; the published Launch Platform sheet

The interlock chain

ParameterValueBasis
Inherited permissivesFour in series ahead of the arm relay: a dual-channel emergency stop, an area-clear key, a muzzle-cover switch and a relief-proven switchthe launcher electrical schematic
Added by this lineFour more, all hard-wired: sector permitted, enclosure closed, base level and wind within limit, with a fifth — round type permitted — at a site that requires canopy roundsnew in the design definition
Arm permissives in seriesEight; nine at a site that requires canopy roundscounted: the four inherited plus the four added, and the round-type permissive where the site requires it
Fire permissiveBoth axis brakes engaged before the breech may opennew in the design definition
One shot per arm actionThe arm relay drops when the fire command completes; the key is turned again for the next shota requirement of the design definition
State after a shotSAFEa requirement of the design definition
Fire commandA local operator action at the operator station onlya requirement of the design definition
The cue's authorityA permissive only; no fire command crosses the cue interfacea requirement of the design definition
Automated or remote-only fire pathNone; the cue interface is capped in the controller specificationa requirement of the design definition
Fail directionAny loss of power, bus, arm relay or interlock returns the mount to SAFE with the breech closed; the watchdog de-energizes every outputa requirement of the design definition
The safety chainHard-wired and dual-channel; never on a networka requirement of the design definition
Where the operator station standsInside the site's secure area, with a direct view of the mount and its engagement sector, joined to the arm relay by a hard-wired dual-channel loop. A second emergency stop stays at the mount.the design definition's proposed meaning of a local fire command; the launcher electrical schematic
Arming from the networkNo workstation elsewhere can arm or fire; site security sees video and status onlya requirement of the design definition
Event recordEvery arm, fire and fault recorded with time, operator and imagery, and not editable in the fielda requirement of the design definition
Energetic materialNone, on the mount or in any round it firesa requirement of the design definition; the schematic's safety-function summary

Air, stored energy and the vessel

ParameterValueBasis
Working pressure30 bardesign value
Relief valve33 bar set point, 110 % of working pressure, sized for full compressor flow and proven by a switch in the arm chainthe pneumatic schematic; a requirement of the design definition
Relief and vent dischargeRouted clear of people and of the building's air intakesthe pneumatic schematic, carried into the roof interface
InstrumentationA 0 to 40 bar transmitter on the bank to the controller, and a local glycerine-filled gaugethe pneumatic schematic
Isolation, vent and drainA lockable manual isolation valve at the bank outlet, and a manual vent and drain at the low point; the bank is ventable to zerothe pneumatic schematic; a requirement of the design definition
Check valveAt the compressor discharge, to prevent backflowthe pneumatic schematic
Air dryerUpstream of the bank, with a dew point below the site minimuma requirement of the design definition
Pressure vesselA certified, registered vessela requirement of the design definition
RegistrationA Canadian Registration Number on the vessel and on the relief device, registration of the assembled piping, inspection at installation and periodic in-service inspectionthe pneumatic schematic's pressure-equipment note
Stored energy in a charged bank4.66 kJ per litre at 30 barcalculated: the adiabatic expansion energy; the formula reproduces the reference bank's published figure
Where the bank and compressor standIn the pedestal, or in a separate enclosure at grade, which is expected for the heat and the noisethe design definition
CompressorElectric, 17 kW shaft powercalculated from the pneumatic work in the Launch Platform design definition
LockoutEvery energy source lockable: the main disconnect, the compressor, the isolation valve, the vent and the gaugea requirement of the design definition
ChargingNobody is inside the charging zone while the bank comes up to pressurethe inherited safety and exclusion-zone data sheet

Power and the network

ParameterValueBasis
Compressor supplyThree-phase; the reference design is drawn to 480 Vthe launcher electrical schematic
Site supplySpecified per site: Canadian institutional sites commonly carry 600 V or 208 V three-phase, and many sites abroad run at 50 Hzthe design definition
Compressor currentAbout 24 A full-load amperes at 480 Vthe inherited load analysis
Control bus24 VDC, physically segregated from the three-phase sidea requirement of the design definition
Voltage-drop limit on the control bus3 %a requirement: sized to the fitted configuration at the corrected conductor resistance
Uninterruptible supplyOn the 24 VDC bus; it carries an orderly return to SAFE and keeps the sensor head running on loss of supplythe design definition
Loss of powerSafe regardless: the breech is normally closeda requirement of the design definition
Electrical installationTo CSA C22.1, with surge protection on every copper entry and the protective bond tied to the building's grounding and lightning protectiona requirement of the design definition; the Launch Platform design definition
Control linkCAN 2.0B, point to point from the controller to the operator station, over fibre beyond the copper runthe controller specification; the design definition
Video and trackEthernet over fibre, segregated, one way and view only to site securitya requirement of the design definition
Cybersecurity design basisIEC 62443, named as a design basisthe design definition
External data portsNone on the mount; the cue interface is physically capped when not in usethe design definition
EnclosureIP65, heated and cooled across the environmental range, with that load on the alternating-current side rather than the control busa requirement of the design definition, and a design choice it records

The sensor head

ParameterValueBasis
What it doesDetects, tracks, classifies and ranges, and passes bearing, range and height to the laying solutiona requirement of the design definition
Who builds itCanadian Shield, in-housethe owner's ruling of 2026-09-11
Day channelA day camera with zoom, for identificationthe design definition's sensor head
Night channelA long-wave infrared thermal imager, for night detection and trackthe design definition's sensor head
RangefinderAn eye-safe laser rangefinder, in a band above 1.4 µm where the retina is not the limiting tissuethe design definition's sensor head
Rangefinder classClass 1 at the aperture to IEC 60825-1, classified by an accredited laboratorya requirement; an eye-safe wavelength is not the same as Class 1, and the class is the laboratory's to settle
Wide channelA wide-field situational camera, for the near zone and the key holder's viewthe design definition's sensor head
Optional channelA passive acoustic array, for bearing-only cueing that tells the optics where to lookthe design definition's sensor head
Not carriedRadar, a radio-frequency detector, a GNSS receiver and an antennaa requirement of the design definition
Aperture ruleEvery channel's clear aperture is at least 1.22 λ ÷ IFOV, so its detector and not diffraction sets its resolutiona requirement of the design definition
Emission controlThe rangefinder emits on the operator's command or on an active track only, and is interlocked off when the stow lock is inthe design definition's sensor head
Links off the headFibre. No copper leaves the sensor head but its supply and its protective bond.a requirement of the design definition
TimeFrom the site network by IEEE 1588, or from the cabinet's own clock. There is no GNSS aboard.the design definition's sensor head
Detection rangeNone is given on this sheetno measured range exists; the figures the design definition works are limits set by optics, and it says in terms that they are not detection ranges
What the doctrine costsDetection is limited by fog, snow and rain, and without radio-frequency detection there is no warning of a drone before it can be seenthe design definition's sensor head
Mounting and searchCo-mounted and boresighted to the barrels, which stops it watching while the mount lays, or on its own mast, which keeps it watching at the cost of a second gimbalthe design definition's search study

Environment, structure and the site

ParameterValueBasis
Low-temperature design case−30 °Cthe round family's environmental design case
Upper temperatureSet per sitea requirement of the design definition, where the upper end is assumed to cover southern Canadian summers with solar gain
CondensateCompressed air carries water that freezes at −30 °C; a dryer and drains are requiredthe design definition
Foundation and roof interfaceDesigned by a structural engineer licensed where the site isa requirement of the design definition
Design basisThe National Building Code of Canada as the province adopts it; the anchorage provisions of CSA A23.3 for the loads above including reversal; CSA S16 and CSA W59; CSA C22.1the design bases named in the design definition and the shop drawing
GeotechnicalThe pier or plinth is sized for overturning and lateral soil capacity from a geotechnical report; frost depth and seismic design are site-specificthe design definition
Environmental loadsWind on the head and pods, snow and ice, drift, seismic and thermal, all to the National Building Code as adopted for the sitethe design definition
Site acceptanceNo mount is armed at a site without a surveyed footprint and a sector cam set cut for that sitea requirement of the design definition and of the safety case
PermitsA building permit and the building official's review, and provincial pressure-equipment registrationthe design definition's roof interface and the pneumatic schematic's note

Anti-tamper and site security

ParameterValueBasis
ArmingThe arm key under key control, with a two-person rule optional. There is no arm path from the network, and no remote fire path to attack.the design definition's anti-tamper table
Doors and coversTamper switches on every door and pod cover. Opening one drops the arm relay, latches FAULT and alarms to site security over a wired input.the design definition's anti-tamper table
Fasteners and anchorsSecurity fasteners throughout; the embedded base, or a locked anchor shroud with tamper-evident marks on the nutsthe design definition's anti-tamper table
RoundsA locked magazine, or ready rounds behind a locked and sensed pod cover, counted at every watch changethe design definition's anti-tamper table
Stored airThe isolation valve lockable, and the bank vented when the mount is unattended where the site rules for charge-on-watchthe design definition's anti-tamper table
Reach and climbingAnything within reach is anti-climb and carries no ligature pointa requirement of the design definition for sites where it applies
Cam setSealed, recorded, and changed only under a controlled procedurethe design definition

Sustainment

ParameterValueBasis
Each useInterlocks, emergency stop and breech fail-closedthe inherited maintenance schedule
Monthly and quarterlyHarness and slew checks monthly; compressor service and breech seal inspection quarterlythe inherited maintenance schedule
Breech sealsLogged by shot countthe inherited maintenance schedule
Per certificateVessel hydrotest and relief proof; a lapsed certificate takes the mount out of servicethe inherited maintenance schedule
Added for this lineSensor window cleaning; dryer and desiccant service; cam-set inspection and seal check; anchor preload check; foundation and roof-penetration inspection; brake holding test; tilt-switch check; uninterruptible-supply testnew in the design definition
AccessPedestal doors onto service racks; lifting points on the head and on each pod; isolation points at the main disconnect, the compressor, the isolation valve, the vent and the gaugethe design definition's maintenance access
LiftingA lifting plan is required: the barrels alone are 298 kg at 6 tubes and 796 kg at 16. On a roof, add fall protection, a service platform and a crane or davit plan.calculated, from the mass ledger; the safety case carries it as a crush hazard
02 · What it is

A Slewing Head on a Cabinet.
The Launch Platform's Chain, Standing Still.


The Pedestal Mount takes the tube module, the breech and the pneumatic chain the Launch Platform already defines, and gives them a fixed pedestal, a sensor head and an interlock chain built for a site that stays where it is.

The stack reads from the ground up: a foundation, a base plate or an embedded socket, a pedestal column whose cabinet holds the power, the controller, the network and the uninterruptible supply, a slewing bearing with the azimuth drive and brake, a head frame with the elevation trunnions, balancer and brake, one pod or twin pods of tubes, and the sensor head. The compressor and the air bank sit at grade in their own enclosure, because both shed heat and noise.

Nothing in the tube module changes. The bore is Ø90.00 mm, the stroke is 3,000 mm, the charge is 30 bar, and each barrel has its own normally closed breech valve that opens in under 5 ms. The rounds are Goose CS-110 and Encapsulator CS-111 at 1.600 kg, and a mixed load is allowed because both share one envelope, one mass and one indexing.

Ø90.00 mm
bore
3,000 mm
stroke
30 bar
charge, air only
1.600 kg
round, either head
Doctrine
Carriers, not munitions. A person arms every shot.

There is no warhead, no fuze, no primer, no propellant and no energetic material on the mount or in any round it fires. A cue is a permissive; no fire command crosses the cue interface, and no automated or remote-only fire path exists.

03 · Size

Three Metres of Stroke.
A Machine Five Metres Tall at Full Elevation.


The largest consequence of inheriting the launch case is height. A three-metre stroke needs a barrel about 3,500 mm long, and a barrel that long, pivoted where it balances, puts the trunnion three metres up.

A pedestal mount seen square on against a plain dark ground: a six-tube pod in three rows of two on a slewing head, a gimballed sensor ball with several windows and a second camera above it, and a tapered eight-sided cabinet column with louvred vents and a hinged door carrying the Canadian Shield mark, standing on a base plate with anchor studs.

The pivot is not assumed. Taking moments about it, with the barrel and its share of the cradle acting at the tube's mid-length and the breech and manifold acting just aft of the breech face, puts the balance point 1.46 m forward of the breech face. The head balances there with no counterweight, and the balance point does not move with tube count, because every tube carries the same masses at the same stations.

That pivot drops the breech 1.41 m below the trunnion at +75°. With clearance under the breech and manifold the trunnion sits 1.66 m above the slewing ring, and 3.03 m above the base plane once the column and the bearing stack are counted. At +75° the muzzle reaches 5.00 m.

The alternative is worse. Moving the pivot to 0.8 m from the breech to lower the machine leaves 513 N·m per tube out of balance, which a counterweight of 392 kg at six tubes and 1,047 kg at sixteen would have to hold — more than half the head again, on a component that is fatigue-loaded and must hold through the shot. The balanced pivot is the recommendation, and the machine is tall because of it.

DimensionValueBasis
Balance point, forward of the breech face1.46 mCalculated by taking moments
Breech drop at +75°1.41 mCalculated
Trunnion above the slewing ring1.66 mCalculated, with clearance under the breech
Trunnion above the base plane3.03 mCalculated, from the modelled column and bearing stack
Muzzle height at +75°5.00 mCalculated
04 · Loads

Eighteen Kilonewtons per Barrel.
The Structure Sees a Step.


The shot load is set by pressure, bore and mass at the instant the valve opens, before the round has moved. It arrives in 0.14 ms, which to a structure whose first mode is in the twenties of hertz is a step.

Thirty bar less one atmosphere acts across 63.617 cm², which is 18,441 N on the closed breech end, the valve body and the barrel-to-breech joint. The obturator's seal drag pulls the tube forward against it, so the net reaction into the mount is 18,191 N — the same number as the source's peak base force, reached by the other route. Over the whole stroke the mean is 9,546 N, and the in-bore impulse, counting the charge gas as well as the round, is 357.3 N·s.

For first sizing the design definition doubles the peak for a step-applied load, giving 36,382 N per barrel, and member checks then take a safety factor of 2.0 on top. A hand modal estimate puts the first bending mode between 22.8 and 34.6 Hz across the pod options; driving a single-degree-of-freedom oscillator with the published force history gives a dynamic load factor of 1.55 to 1.74 undamped and 1.50 to 1.69 at 2 % damping. The factor of 2.0 therefore carries 15 % to 29 % of margin over the first mode, and it stays until a modal analysis replaces it.

At the trunnion height the stroke forces, one barrel puts 110.3 kN·m of overturning into the base at 0° elevation on the equivalent static load. Overturning is worst at low elevation, where the reaction is almost wholly horizontal.

Per barrelValueBasis
Gas load on the breech18,441 NCalculated
Peak net reaction into the mount18,191 NCalculated; it reproduces the source's peak base force
Mean base force over the stroke9,546 NCalculated
In-bore impulse357.3 N·sCalculated
Equivalent static load36,382 NCalculated, at a step factor of 2.0
Factored load for member checks72,764 NCalculated, at a safety factor of 2.0 on top
Base overturning moment110.3 kN·mCalculated, at the modelled trunnion height
A close view of nine tube muzzles in three rows of three on a near-white ground, each polished steel bore ring set in a black tube body, with bolted clamp bands and brass fittings running back along the pod frame.
05 · Pointing and holding

The Drives Lay the Tubes.
The Brakes Carry the Shot.


A pod of six to sixteen tubes is an order heavier than the reference four-tube cradle, and the shot torque it puts on the axes is orders above any laying torque. The two are different jobs, done by different parts.

A pedestal mount seen head on from the front on a near-white ground: twin pods of eight tubes each, four rows of two, carried on short arms either side of a central head box with the Canadian Shield mark, a gimballed sensor ball above it, and a louvred eight-sided cabinet column on a base plate with lifting shackles and forklift pockets.

A single centred pod's polar moment about the azimuth axis runs from 646 kg·m² at six tubes to 1,738 kg·m² at sixteen. Putting the pods out to twin heads at an illustrative half-metre offset raises the sixteen-tube case to 2,054 kg·m². Those are the numbers the drives work against, and the pointing performance the line offers is a decision that follows from them rather than one this sheet fixes.

The shot is a separate matter. A barrel whose bore line sits off the axis applies the peak reaction on that lever: 2,183 N·m at six tubes, 3,274 N·m at sixteen on a centred pod, and 12,370 N·m on twin eight-tube pods at half a metre. The brakes are sized at twice the worst torque of the configuration fitted, and the fire command waits on both of them engaged. The single centred pod is cheaper in brakes by about a factor of four, which is the strongest engineering argument in the pod decision.

If a brake were to let go for one shot, the angular impulse would turn a sixteen-tube head at 2.1°/s and a six-tube head at 3.8°/s. Over the time the round is in the bore that is well under a tenth of a degree, so the shot in flight is unaffected. What a slipping brake does is back-drive the reducer and the motor, and move the lay for the next shot. The brake is sized on torque, and it is tested for holding.

Single centred pod6 tubes91216
Azimuth moment of inertia, kg·m²6469691,3031,738
Elevation moment of inertia, kg·m²6429691,2921,738
Worst shot yaw torque, N·m2,1832,1833,2743,274
Worst shot pitch torque, N·m1,0912,1832,1833,274
Design brake torque, kN·m4.44.46.56.5
Rotating mass, kg6489581,2671,679
Step 1

Mechanical hard stops

At the fixed limits of both axes, independent of everything above them.

Step 2

Cam-operated limit switches

On both axes, wired into the sector permissive ahead of the arm relay. The cam set is site hardware, cut from the site's surveyed footprint map, sealed and recorded.

Step 3

Software refusal

A laying solution outside the envelope is refused before the drives move.

Step 4

The site no-fire map

Loaded into the laying software as a cross-check. It never replaces the cam switches.

06 · The interlock chain

Eight Permissives in Series, and a Ninth.
Then One Barrel, and Back to SAFE.


The mount inherits the Launch Platform's four series permissives and adds four of its own, with a fifth at a site that requires canopy rounds, all hard-wired ahead of the arm relay. Any one of them open leaves the relay de-energized and the mount safe.

To a series chain a cut wire and a pressed stop are the same event, which is why the chain is hard-wired and dual-channel and never sits on a network. With every permissive in the chain made the arm relay energizes, and fire is a local operator action. The relay then drops when the fire command completes, so the key is turned again for the next shot and the mount returns to SAFE between shots. Each arm action releases one barrel, and one solenoid is energized at a time.

Where a site requires canopy rounds, a further interlock reads a mechanical round-type key at the breech and confirms the selected tube holds one, and the site's cam set carries the minimum lay elevation the canopy's release threshold implies. The sector cam set, the tilt switch and the anemometer are all hardware, independent of the laying software and of the encoders.

PermissiveKindWhat it confirms
Emergency stop, dual channelInheritedTwo normally closed channels agree that no stop is pressed
Area-clear keyInheritedA named person has walked the near zone, as defined for the site, and turned the key
Muzzle coverInheritedThe cover is off the muzzle
Relief provenInheritedThe relief path is proven before the mount will arm
Sector permittedAddedCam switches on both axes confirm the tubes point into a permitted cell of the site's cam set
Enclosure closedAddedEvery cabinet door and pod cover is shut and sensed
Base levelAddedA tilt switch confirms the base is within tolerance
Wind within limitAddedA wired anemometer and a threshold relay
Round type permittedAdded, at a site that requires canopy roundsA breech switch reads the round-type key and confirms the selected tube holds a canopy round
Brakes setAdded, fire permissiveBoth axis brakes are engaged before the breech may open
The boundary
The cue proposes. It never authorizes.

Bearing, range and height cross the cue interface as a permissive. No fire command crosses it, no workstation elsewhere on the network can arm or fire, and any loss of power, bus, arm relay or interlock returns the mount to SAFE with the breech closed.

07 · The sensor head

Eyes on the Head, on Fibre.
Nothing on It Transmits.


Detect, track, classify and cue are Canadian Shield's own. The head is passive but for an eye-safe rangefinder under emission control, and every link off it is fibre.

The head carries a day camera with zoom for identification, a long-wave infrared imager for night detection and track, a wide-field situational camera for the near zone and the key holder's view, and an eye-safe laser rangefinder for range. A passive acoustic array is optional, and earns its place as a bearing-only cue that tells the optics where to look. It carries no radar, no radio-frequency detector, no GNSS receiver and no antenna, and the design reserves nothing for one.

The design definition sets two requirements on the optics rather than naming any product. The first is that every channel's clear aperture is large enough that its detector, and not diffraction, sets its resolution — which at long-wave infrared is a demanding number, and it sizes the head, its mass and its window heaters. The second is that the rangefinder is Class 1 at the aperture to IEC 60825-1, classified by an accredited laboratory: an eye-safe wavelength is a necessary condition, not a sufficient one, and the class depends on pulse energy, divergence, pulse rate and aperture.

No detection range is given, and the design definition gives none. The figures it works are limits set by optics on a clear day against a target of known size and aspect. They leave out atmospheric transmission, contrast against sky or ground, thermal contrast on a battery-electric multirotor, target aspect and the search problem. A detection range for a named target class comes from trials.

WHAT IT CARRIES

EO, LWIR, a wide camera and a rangefinder

Day, night, near zone and range, on one boresighted head, with a passive acoustic array optional.

WHAT IT DOES NOT

No radar, no radio detection, no GNSS, no antenna

The design carries none of them. Every data path on the mount is wired or fibre, and no copper leaves the head but its supply and its bond.

WHAT THAT COSTS

Weather, and no warning before line of sight

Detection is limited by fog, snow and rain, and without radio-frequency detection there is no warning of a drone before it can be seen. The design definition states the cost so the decision is made knowing it.

08 · Power, air and the network

Three-Phase to the Compressor.
Fibre for Everything That Leaves.


One three-phase load, one segregated control bus, one hard-wired safety chain, and fibre for every data run off the mount.

The compressor is the three-phase load. The reference design is drawn to 480 V, and the motor and supply are specified per site, because Canadian institutional sites commonly carry 600 V or 208 V and many sites abroad run at 50 Hz. Everything else runs on a 24 VDC bus kept physically apart from the three-phase side, sized to the fitted configuration inside a 3 % drop limit. An uninterruptible supply on that bus carries an orderly return to SAFE and keeps the sensor head running; loss of supply is safe regardless, because the breech is normally closed.

On the air side the compressor charges a certified, registered vessel through a filter, a dryer and a check valve. A relief valve set at 33 bar, 110 % of working pressure and sized for full compressor flow, stands above it and is proven by a switch in the arm chain. A transmitter reads the bank for the controller, a local gauge reads it for a person, and a manual isolation valve, vent and drain take the stored air out of the machine. The dryer is not optional at a site that sees −30 °C: compressed air carries water, and water freezes.

The network runs in three parts that never meet. The safety chain is hard-wired and dual-channel. The control link is a point-to-point CAN bus from the controller to the operator station, over fibre beyond the copper run. Video and track run on segregated Ethernet over fibre, one way and view only to site security. There are no external data ports on the mount, and the cue interface is physically capped when not in use.

ElementWhat it isBasis
CompressorElectric, 17 kW shaft power, on three-phaseCalculated from the pneumatic work
Site supplySpecified per site; the reference design is drawn to 480 VThe electrical schematic and the design definition
Control bus24 VDC, segregated, inside a 3 % drop limitA requirement of the design definition
Relief valve33 bar set point, full compressor flow, proven in the arm chain110 % of working pressure
Stored energy in the bank4.66 kJ per litre at 30 barCalculated, adiabatic expansion energy
VesselCertified and registered, with a Canadian Registration Number on the vessel and the relief deviceThe pressure-equipment note on the pneumatic schematic
Safety chainHard-wired, dual-channel, never on a networkA requirement of the design definition
Data off the mountFibre, segregated, view only to site securityA requirement of the design definition
09 · Siting and the safety case

Where a Miss Can Land.
And What Has to Be True First.


The occupied-site human-safety case is this line's first design driver, and it is open. What follows is what the engineering says about the ground a miss can reach, and the conditions the charter sets before any page may go further.

The safety case treats every round fired as a miss, because no hit or capture probability has been measured. On that basis, and at the round's design drag coefficient of 0.35 from ground level in still air at sea level, a missed round lands out to 1,659 m from the mount, and no elevation in the envelope lands one below 7.3 kJ. The round's terminal velocity is 137.9 m/s, so it never slows below about 95 m/s on any arc. A flat lay puts the round down further away; a steep lay puts it down nearer, not softer, returning from nearly a kilometre up.

The drag coefficient is the weakest figure in the chain. If the fairing the round's design definition names as a live option halved it, the reach would grow to 2,215 m, so a site survey carries the halved-drag radius until the drag is measured. Every footprint figure here is only as good as that coefficient, and it is given with it.

What the mount does about it is hardware. The sector cam set is cut from a surveyed footprint map for that one site and sealed; the mount will not arm with the sector permissive open; and no mount is armed at a site without both. Sectors change where a miss lands, not how hard it lands, and the safety case says so in terms.

The miss, at Cd 0.35Value
Maximum range across the envelope1,659 m, at 39°
Minimum impact energy across the envelope7.3 kJ, at about 30°
Impact energy at 5°16.7 kJ, at 525 m
Impact energy at the +75° mount limit9.7 kJ, at 788 m, from an apogee of 962 m
Terminal velocity of the round137.9 m/s
Survey radius if the drag were halved2,215 m

What the charter allows this sheet to say.

  • That the Roof Mount and the Pedestal Mount are in engineering.
  • That human safety where people are present is the line's first design driver.
  • Every figure above, with the drag assumption it rests on.

What it does not say, and why.

  • It does not say either mount suits a site with people on it. The charter sets seven conditions before any page may, and none of them is met.
  • It gives no descent rate, no landing energy and no drift footprint for the canopy round option, because the safety case bars those until the canopy test program is complete. No canopy has been made, packed or deployed.
  • It gives no detection range, because none has been measured.
  • It is not an offer, and counsel has still to advise on who may lawfully own and operate either mount.
10 · The round option

A Canopy in the Round's Body.
A Mechanical Release, and Nothing That Burns.


On the owner's ruling of 2026-09-11 the line opened a miss canopy as an option on the round rather than as a new round. It is engineering with a test list attached, and this sheet gives its constraints and not its results.

The option is a packed canopy in the round's forward body bay, aft of the nose and head interface, so one option serves the kinetic head and the Encapsulator head alike. It carries no energetic material, no electronics and no power source. It opens by a positive mechanical action and initiates nothing: what it opens is a fabric bay. The round stays at 1.600 kg with the same envelope, the same magazine pitch and the same launch case, and the option's mass comes out of the Goose nose or the Encapsulator ballast rather than being added.

Two things bind it. The first is that every automatic post-launch release needs a lock driven by the launch itself, and a lock plus a release condition is the architecture a fuze's safety-and-arming device uses. That the mechanism opens a fabric bay and starts nothing is the company's own distinction, and no regulator has yet ruled on it; counsel answers before any trigger is chosen. The second is stability: the option's mass is capped by the round's static margin rather than by the mass budget, and the design definition holds it to 150 to 250 g with the margin staying inside the 1.5 to 2.5 calibre band on both baselines.

A canopy round is a steep-lay round. No release has been chosen. The one the design definition recommends for study trips as airspeed decays, and were it set at a 60 m/s threshold it would open before landing only above 54.5° of quadrant elevation, with the round below that landing as any miss would. Where a site requires canopy rounds, the cam set enforces in hardware the minimum elevation the chosen release implies, and the round-type key at the breech enforces the round.

What the engineering fixesValueBasis
Round mass, unchanged1.600 kgA requirement of the design definition
Option mass band at R0.3150 to 250 gBuilt up by element and capped by the static margin
Static margin with the option fitted1.56 to 1.91 calibres across every caseCalculated; the design band is 1.5 to 2.5 calibres
Free volume in the forward body bay315 cm³Calculated from the bay's bore and clear length
Minimum lay elevation at a 60 m/s threshold54.5°Calculated from the modelled arcs, for the airspeed-decay release recommended for study
Steady opening load at that threshold2.26 kNCalculated, before any opening-shock factor
What a drogue stage would take off that loadA factor of 5.8Calculated, for a drogue slowing the round to 25 m/s first
Energetic material in the optionNone; a reefing cutter is barred with itA requirement of the design definition
11 · Who it is for

The People Who Hold the Key.
And the Ground a Miss Can Reach.


A Pedestal Mount is bought by the authority that owns the site, surveys the ground around it, accepts what the survey shows and holds the arm key.

What a buyer brings.

  • A fixed site, and three-phase power on it.
  • A survey of every parcel a miss can reach, and the authority to accept or refuse what it shows.
  • A structural engineer licensed where the site is, for the foundation or the roof interface.
  • An accountable authority and a regulator who will name the tolerable risk for the site.
  • A named operator who holds the arm key and turns it for every shot.
  • A secure area for the operator station, with a direct view of the mount and its sector.

What the mount is not.

  • Not a remote weapon station: a person arms every shot, and there is no arm or fire path from the network.
  • Not an autonomous system: a cue proposes, and no fire command crosses the cue interface.
  • Not a radio system: the design carries no antenna, no radio and no GNSS, and it neither jams nor spoofs.
  • Not an energetic system: no warhead, no fuze, no primer, no propellant, and none in the canopy option.
  • Not ready for a site with people inside the ground a miss can reach. The charter's seven conditions stand ahead of that, and none is met.
  • Not an offer: enquiries are screened, and international transfer is subject to Canadian export permits taken per shipment.
12 · Configurations

One Head, One Bore.
Several Ways to Fill and Stand It.


What changes between builds is the number of tubes, how they are grouped, how the mount stands on the ground, how it is loaded and where the shot volume sits. The bore, the charge pressure and the stroke do not change with any of them.

POD SIZE

Six, nine, twelve or sixteen tubes

The design definition works every load, mass, inertia and brake figure across all four and rules none of them. Tube count moves the rotating mass from 648 kg to 1,679 kg, the azimuth moment from 646 to 1,738 kg·m² and the design brake torque from 4.4 to 6.5 kN·m. It does not move the balance point or the trunnion height.

ONE POD OR TWO

A single centred pod, or twin pods either side

Twin pods move each pod's mass out from the azimuth axis, which raises the polar moment and, far more sharply, the shot yaw torque: 12,370 N·m against 3,274 N·m at the same tube count. The brakes then cost about four times as much, which is the engineering argument for the single centred pod.

THE BASE

Bolted plinth, embedded socket, or four levelling legs

A bolted anchor on a concrete plinth uses cast-in headed rods, a base plate on levelling nuts and non-shrink grout, with the nuts under a locked shroud. An embedded steel socket cast into a reinforced pier puts the anchors out of reach from outside and gives a stiffer, lower base, at the cost of being permanent. Four screw-jack legs on pads suit a transportable build and must be ground-anchored or ballasted, because legs creep and a base that walks under a shot is not a base.

LOADING

A magazine, or pre-loaded pods

The reference auto-index magazine holds twenty-four rounds behind a lock, with a motor and an encoder and no pyrotechnics. Pre-loaded pods hold one ready round per tube behind a locked, sensed pod cover and reload at the breech or by pod exchange; there is then no indexer to design, and the ready rounds sit in the tubes.

WHERE THE AIR SITS

A reservoir at each breech, or one plenum on the head

A reservoir at each breech keeps the shot volume where the interior-ballistics model puts it, at the cost of a certified, registered, individually inspected vessel on a rotating head for every tube. One shared plenum on the head, fed through the azimuth by a hose loop, is far lighter and needs no rotary union for the ±170° travel, but it must refill between shots. The flow analysis that decides it needs a line and valve geometry that does not exist.

THE ROUND OPTION

The miss canopy, on either head

A packed canopy in the round's forward body bay, with a mechanical release, no energetic material, no electronics and no power source. It sits aft of the nose interface, so one option serves both heads. Where a site requires it, the round-type key and the cam set enforce both the round and its minimum lay elevation.

13 · Doctrine and safety

Carriers, Not Munitions.
A Human Arm Action for Every Shot.


The lines the mount holds on every build and for every customer, and the one thing this sheet does not say.

Where next

The Rest of the Line.
A Sheet for Every Product.


The page this sheet specifies, and the sheets beside it in the line.

The product page

Pedestal Mount

The page this sheet specifies, with the pictures and the reasoning.

Institutional · spec sheet

Roof Mount

A launch mount on a building roof, carried into the primary structure.

Every sheet

The spec sheet index

Every product and platform on one sheet each, on the web and as a PDF.

The conversation

Bring the Site and the Survey.
The Answer Comes Back in Writing.


A first conversation needs the site, the three-phase power already on it, the ground within the survey radius and who owns it, the authority that will accept the residual risk, and who would hold the arm key.

CDN-PROD-SPC-019 · R1.0 · Issued 2026-09-11 · PDF, 28 pages, 943 KB

Not an offer. Enquiries are screened, international transfer is subject to Canadian export permits taken per shipment, and all designs, systems and technologies shown are patent pending.